Category > Development Updates

Regency Place Project Update – July 17

Following on from our May update, we are delighted to share with you the latest progress for Regency Place. All foundation piling and integrity testing is now complete, along with the lift shaft and crane base. The drainage installation is…

Madison House Project update – July 17

Following on from our May update, we are delighted to share with you the latest progress for Madison House. Drainage on site is now almost complete along with the main superstructure. Waterproofing to the roof has commenced and steel erection…

Churchill Place Project Update – July 2017

Following on from our March update, we are delighted to share with you the latest progress for Churchill Place. We have now completed setting out apartments on all floors and installation of new windows is ongoing. Removal of the redundant…

Ridley House Project Update – June 2017

Following on from our March update, we are delighted to share with you the latest progress for Ridley House. Kitchens and bathrooms are being fitted and painting will commence shortly. Balcony roofs are watertight and are now being rendered. The Winter Gardens…

SGUV progress picture 1

St George’s Urban Village Project Update – May 2017

Following March’s update, we are delighted to share with you the latest progress for St George’s Urban Village. Groundwork is now almost complete, along with piling across the development. Steelwork is now underway and has been completed for block 5.…

Granville Lofts progress photo 1

Granville Lofts Project Update – May 2017

Following March’s update, we are delighted to share with you the latest progress for Granville Lofts. The tower crane has now been erected and work on the foundations is in progress. Steelwork has started on the retaining wall for the new…

The Kettleworks May progress picture 1

The Kettleworks Project Update – May 2017

Following on from our March update, we are delighted to share with you the latest progress for The Kettleworks. Alterations are now complete on the first block and work on the roofing is ongoing. The steel frame is now 90% complete…

Churchill Place Project Update – April

Seven Capital is pleased to share with you the first progress update on site at Churchill Place in Basingstoke. The internal ‘soft strip-out’ is finished on all floors. Lift removal is almost complete and some areas of additional demolition to existing…

St George’s Urban Village Project Update – March 2017

We are delighted to share with you the first progress update for St George’s Urban Village. Groundworks have been completed on over 50% of the development and piling is almost finished. The next stage will see the progression of groundworks…

Ridley House Project Update – March 2017

Following on from our December update, we are delighted to share with you the latest progression at our development, Ridley House. The crane has now been removed and the building will be water tight within the next two weeks. The…